HIRARC Form

Hazard Identification, Risk Assessment and Risk Control. Layout follows the HIRARC form in the DOSH Guidelines for HIRARC 2008 (Appendix C).

Print on A4 landscape, or choose "Save as PDF" in the print dialog. Page 2 holds the rating tables and risk matrix. Use one form per work process.

CompanyConducted by (name, designation)
Process / locationDate (from ... to ...)
Approved by (name, designation)Review date
Approval dateNext review date
1. Hazard identification2. Risk analysis3. Risk control
No. Work activity Hazard Which can cause / effect Existing risk control (if any) Likeli­hood (L) Severity (S) Risk (L×S) Recommended control measures PIC (due date / status)
1
2
3
4
5
6
7

Rate L and S with the existing controls in place. Re-assess after the recommended controls are implemented. Include routine and non-routine activities (maintenance, cleaning, breakdowns).

Rating guide

Likelihood (L)ExampleRating
Most likelyThe most likely result of the hazard / event being realised5
PossibleHas a good chance of occurring and is not unusual4
ConceivableMight occur at some time in future3
RemoteHas not been known to occur after many years2
InconceivableIs practically impossible and has never occurred1
Severity (S)ExampleRating
CatastrophicNumerous fatalities, irrecoverable property damage and productivity5
FatalApproximately one single fatality, major property damage if hazard is realised4
SeriousNon-fatal injury, permanent disability3
MinorDisabling but not permanent injury2
NegligibleMinor abrasions, bruises, cuts, first aid type injury1

5×5 risk matrix (Relative risk = L × S)

Likelihood (L)Severity (S)
12345
5510152025
448121620
33691215
2246810
112345

Action by risk level

ScoreRiskAction
15 to 25HighImmediate action to control the hazard using the hierarchy of control. Record actions and completion date on this form.
5 to 12MediumPlanned approach to control the hazard; apply temporary measures if required. Record actions and completion date.
1 to 4LowMay be acceptable; further reduction may not be necessary. If it can be resolved quickly and efficiently, implement and record the control.

Hierarchy of control

1. Elimination  ·  2. Substitution  ·  3. Engineering controls (isolation, guarding, ventilation, lockout)  ·  4. Administrative controls (safe work procedures, permits, training, supervision, job rotation)  ·  5. PPE (last line of defence)

HIRARC team members (name, designation)
Person in charge of area (sign)
Management approval (sign, date)

DOSH guidance: communicate the HIRARC to employees, keep records for at least 3 years, and review every three years or whenever the process or activity changes. Risk assessment is a duty under section 18B of the Occupational Safety and Health Act 1994.